1) Make sure that the place where the FAAC CITY traffic bollard is to be installed is not a cavity; if
this situation is present, partially protect the FAAC CITY traffic bollard with a drainage channel
equipped with covering grid.
2) Dig up to a depth of about 1.30 m (275 H600) or about 1.50 m (275 H800); the cross-section shall
have a side of about 1 m (fig. 1 and fig. 2).
3) Make sure that the ground is able to absorb water: pour about 40 l water in the dig and check if
draining takes place within 30 minutes. If this is not the case, discharge rainwater by means of a
pipeline with a diameter of 60mm connected to the drainage system or, as an alternative,
connected to a pit equipped with a drainage system (i.e. motor pump), having a depth greater
than the FAAC CITY pit for the collection and drainage of rainwater.
4) Introduce gravel (grain with a diameter of approx. 8 - 20 mm) to obtain a thickness of about 30
cm, taking care to compact it well to avoid future settlements.
5) Install the metallic pit complete with counter-frame, taking care to position it vertical. The top
level of the counter-frame must be approx. 10mm higher than the floor surface (to limit the inlet
of rainwater in the pit). Place the pit checking the reference of the counter-frame according to
the sense of direction (fig. 1 and fig. 2).
6) After pit installation, lay a flexible sheath, internal diameter 45mm, from the electrical
connection in the pit to the drive control station.
7) Cast concrete all around the pit, up to approx. 10cm from the floor surface, and make sure that
the anchors supplied with the pit are correctly positioned. Once the pit has been positioned,
finish the street surface using the same type of material (fig. 3 and fig. 4).
8) Lay the necessary pipes for the connection between the control unit and any additional device
(i.e. traffic lights – inductive loops – card reader – etc.) and every other bollard, if present. Then
prepare the electrical connection and the earthing (fig. 5).
N.B.: every pipe must be laid in compliance with the current rules.
AUTOMATIC TRAFFIC BOLLARDS WITH PIT
FAAC CITY 275 H600 and 275 H800
INSTALLATION DIAGRAM
FAAC S.p.A. Via Benini, 1 40069 Zola Predosa Bologna (Italia) tel. +39 051 61724
- 5 -
www.faac.it