In the event of faults during commissioning, see chapter "Troubleshooting and fault
elimination".
Switch-on sequence
1. Before connecting the supply voltage check the wiring for completeness and short-circuits.
2. Switch on the supply voltage for the Drive PLC and the PC.
3. Load the required project into the Drive PLC, using the software "Drive PLC Developer Studio"
(DDS).
(
4. If you do not want to use the DDS for program control, then you can remove the connection
between the Drive PLC and the PC. Switch off the supply to both instruments before you do
this.
Controlling the program
You have various options for controlling the program in the Drive PLC:
Control through
Software Drive PLC Developer
Studio (DDS)
Software "Global Drive
Control (GDC)
Control" (GDC)
Keypad XT 9371BC
*)
Lenze setting
L
(
49)
"Drive PLC Developer Studio - Getting started", Chapter 4.4)
Program function
Start, Stop, Reset
Automatic start
Sta t, Stop, eset
Start, Stop, Reset
EDK10200EV3 DE/EN/FR 6.0

Commissioning

Setting/Parameterization
Manual DDS - "Getting started", Chapter 4.4.4
and Chapter 4.4.6
*)
Program does not start
C2104 = -0-
automatically after switch-on
C2104 = -1-
Program starts automatically
after switch-on
*)
C2108 = -0-
Function executed
C2108 = -1-
Start program
C2108 = -2-
Stop program
C2108 = -3-
Reset program