Herunterladen Inhalt Inhalt Diese Seite drucken

Disposal - Honeywell BA195 miniBA Einbauanleitung

Systemtrenner
Vorschau ausblenden Andere Handbücher für BA195 miniBA:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 1
8.1 Inspection
• Frequency: every 6 month (depending on
local operating conditions)
• To be carried out by an installation company
• Inspection with a test control unit and mainte-
nance-set (see accessories)
8.1.1 Testing discharge valve
Take note of the instructions of the test control
unit TKA295 or TK295
1. Procedure according to instruction of the test control
unit TKA295 resp. TK295
Quick test for the discharge valve:
• Lower the inlet pressure
o if the discharge valve opens (it drops), the
function is o.k.
8.1.2 Testing outlet check valve
Take note of the instructions of the test control
unit TKA295 or TK295
1. Procedure according to instruction of the test control
unit TKA295 resp. TK295
8.2 Maintenance
We recommend a planned maintenance
contract with an installation company
In accordance with DIN EN 1717 a regular mainte-
nance must be taken.
Frequency: every 1-3 years (depending on local
operating conditions)
To be carried out by an installation company
8.2.1 Cartridge insert
1. Close shutoff valve on inlet
2. Release pressure on outlet side (e.g. through water
tap)
3. Close shut off valve on outlet
4. Unscrew discharge connection
5. Remove elbow pipe
6. Remove retaining ring
7. Replace cartridge insert and lip seal
• Don't disassemble cartridge insert to indivi-
dual parts!
8. Reassemble in reverse order
o push down the cartridge insert till it snaps in
9. Test function (see chapter inspection)
Honeywell GmbH
GB
8.2.2 Check valve
1. Close shutoff valve on inlet
2. Release pressure on outlet side (e.g. through water
tap)
1. Close shut off valve on outlet
2. Exchange check valve
Check valve will be destroyed after demounting
3. Test function (see chapter inspection)
8.3 Cleaning
• To be carried out by an installation company
• To be carried out by the operator
If necessary, the cartridge insert can be cleaned.
Do not use any cleaning agents containing
solvents and/or alcohol to clean the plastic
parts!
Detergents must not be allowed to enter the
environment or the sewerage system!
1. Close shutoff valve on inlet
2. Release pressure on outlet side (e.g. through water
tap)
1. Close shut off valve on outlet
2. Unscrew discharge connection
3. Remove elbow pipe
4. Remove retaining ring
5. Clean or replace cartridge insert and lip seal
• Don't disassemble cartridge insert to indivi-
dual parts!
6. Reassemble in reverse order
o push down the cartridge insert till it snaps in
7. Test function (see chapter inspection)

9. Disposal

• Dezincification resistant brass housing
• High-quality synthetic material valve cartridge
• High-quality synthetic material or red bronze check
valves
• Sealing elements made of elastomer materials
suitable for drinking water
• High-quality synthetic material discharge connec-
tion
Observe the local requirements regarding
correct waste recycling/disposal!
6
MU1H-1233GE23 R0606

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis