If damage can occur due to a failure of the pumping station, for example due
to a power failure or technical defect, an alternative system must be available
as backup e. g. emergency power supply, double pumping station, network-
independent alarm, etc.
ATTENTION!
Activation of the "high water level" alarm is delayed while the system attempts
to fix the problem with two pumping test cycles. On completion, if the problem
persists the alarm will then sound.
ATTENTION!
The lifting unit must not be thrown or dropped during transport or installation.
The lifting unit must not be lifted by the power cable!
>
Observe the correct operating voltage (see "Technical Data")
>
Never place the power plug in water
>
Connect the lifting unit to a properly installed electrical socket (in compliance
with VDE and the power supply company regulations) protected by at least
a 10 A (slow-blowing) fuse
>
For units of protection classification I, all exposed conductive parts are con-
nected with a protective earth conductor. Before the unit is put into operation,
an electrically skilled person must check that the protective earth cable is
properly connected
>
Temperatures higher than those permitted cause the pump to be shut off by the
temperature limiter. After the temperature limiter is triggered, disconnect the
pump from the electric system before correcting the cause of the fault, other-
wise it will switch on automatically once cooled down