The connector of the connection cable must be splash-
proof.
When running the connection line observe that it does not
interfere, is not squeezed, bended and the plug connection
does not get wet.
Do not use the cable for purposes for which it is not meant.
Protect the cable against heat, oil and sharp edges. Do
not use the cable to pull the plug from the socket.
Wind off completely the cable when using a cable drum.
Regularly check the extension cables and replace them if
they are damaged.
Do not use any defective connection cables.
When working outdoors, only use extension cables
especially approved and appropriately labelled for outdoor
use.
Do not set up any provisional electrical connections.
Never bypass protective devices or deactivate them.
The device must be connected via the fitted PRCD
(residual-current-operated circuit breaker).
The electrical connection or repairs to electrical parts of
the machine must be carried out by a certified electrician
or one of our customer service points. Local regulations –
especially regarding protective measures – must be
observed.
Repairs to other parts of the machine must be carried out
by the manufacturer or one of his customer service
points.
Use only original spare. Accidents can arise for the user
through the use of other spare parts. The manufacturer
is not liable for any damage or injury resulting from such
action.

Preparing for commissioning

To achieve perfect function of the machine, follow the
notes given in these instructions
You have to attach the following parts:
Base frame
Cooling water pump
Assembly of the base frame and the cooling water
pump
-
B
D
1. Assemble the main pillars (1) with the screws (4) and the
spring washers (5) on the frame.
2. Screw the clamp holders (6) with the star handle nuts (7) and
the coach bolts (8) on the frame (3).
3. Put the trough (9) into the frame (3).
4. Put the cooling water pump (26) into the intended gap of the
D
trough.
5. Fill water into the trough until the cooling water pump is
covered with water.
6. Put the radial tile cutter into the trough.
B
C

Commissioning

Mains connection
Compare the voltage given on the machine model plate e.g.
230 V with the mains voltage and connect the saw to the
relevant and properly earthed plug
Alternating current motor:
Use a shockproof plug, mains voltage 230 V with residual
current circuit breaker and 10 A inert fuses.
Use connection cable or extension cable respectively with a
cross section of at least 1,5 mm².
Daily checks of the PRCD (residual-current-operated
circuit breaker)
The device must be connected via the residual-current-
operated circuit breaker (PRCD).
1. Directly plug the PRCD into the outlet (vertical).
2. Press the green Reset key – you will hear a click and the
indicator will light up orange.
3. To check the PRCD press the blue test key. The indicator
panel should no longer light.
4. Press the Reset key again – the indicator panel will
light up orange.
5. The machine can be startet.
Switch on
Do not use any device where the switch can not be
switched on and off. Damaged switches must be repaired
or replaced immediately by the customer service.
Check that the PRCD is operative: indicator panel orange.
Press the green button ( I ) on the
switch. At the same time, check
whether the rotating direction of the
cutting-off wheel corresponds to
the indicated rotational direction on
the protection cover (arrow).
If there is a power cut, the machine switches off automati-
cally. To switch on again, first press the red and then the
green button.

Switching off

Press the red button ( 0 ) on the switch.
16
Perform this check once in a
day.
When changing the location
„Reset"
no further test is required.
„Test"