Installing this industrial chiller is very simple.
The first installation of a new machine can be carried out by following these
steps:
④.PLUG IN THE POWER SUPPLY AND TURN ON THE POWER
SWITCH. (DON'T START WITHOUT WATER IN THE TANK!)
(1) The power switch is turned on and the circulating pump of the chiller
starts to work. The first operation may cause more bubbles in the pipe,
causing occasional alarms for traffic, but after a few minutes of operation, it
will return to normal.
(2) After the first start-up, the water pipe must be checked for leakage
immediately.
PROCEDURE
①.OPEN THE PACKAGE TO CHECK IF THE
MACHINE IS FIXED AND ALL NECESSARY
ACCESSORIES ARE COMPLETE.
②.OPEN THE WATER SUPPLY INLET TO SUPPLY
COOLING WATER (DON'T SPILL THE WATER
OUT!).
Observe the water level gauge and add water slowly,
taking care not to let the water overflow! For the
cooling of carbon steel equipment, an appropriate
amount of cooling water additive (anti-corrosion water
aqua) should be added to the water. Users in cold
regions should use non-corrosive antifreeze.
③.CONNECT THE INLET AND OUTLET PIPES
ACCORDING TO THE SYSTEM CONDITIONS.
- 5 -