Installation in exposed drainage pipe

Fit the connection piece (2) between the pump connec-
tion socket (1) and the connector (3), and lock both quick-
release closures (4).
4.7
Installing the cable conduit
Route the cable conduit (DN70) up to the cable gland (1)
(DN50) in the drain body and fit.
Use max. 45° bends for changes in direction.
If the cable conduit is to be installed in the upper section,
it must be carried out with the KESSEL hole saw art. no.
500101 or a standard hole saw Ø 60 mmand the pipe
penetration seal art. no. 850114.
The connection of the electric cables is explained in the
enclosed control unit instructions.