Herunterladen Inhalt Inhalt Diese Seite drucken

AFRISO ProCalida EF1 Betriebsanleitung Seite 39

Heizkreisverteiler
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 1
6
Commissioning
6.1
Commissioning the product
.Max. 
E
1 1/2 x
Commissioning
B
A
B
C
1. Connect the hose (D) to the
end cap with the hose con-
nection or to the boiler filling
and drain valve KFE (E).
2. Open the white hand wheel
for filling and flushing.
3. Open the return valve of the
first heating circuit (A).
Max. 
4. Slightly open the flow valve
of the first heating circuit
1 1/2 x
(C).
5. Close all other valves (B).
6. Fill the heating circuit with a
maximum of 5 bar and flush
it.
7. Fully open the flow valve (C)
as soon as water flows into
D
the heating circuit.
8. Close the flow valve and the
return valve of the filled
heating circuit.
9. Repeat the procedure 1 to 5
for filling and flushing for all
other heating circuits.
ProCalida® EF 1
EN
17

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis