04.04
Material inspection
The components are to be checked for damage prior to
installation. Damaged components must not be installed.
04.05
Cutting open the pipe connections
The openings for the connections are still closed when they
are delivered to the building site and must be opened using a
fine-toothed saw (e.g. jigsaw) as required. The cuts may only
be made along the markings provided; construction
elements that are wrongly sawn out must be replaced. The
component structure must not be damaged outside the cut
contours provided.