Commissioning
6.1
Commissioning the product
INCORRECT PRESSURE IN INTERSTITIAL SPACE
If the operating pressure in the interstitial space does not meet the specifica-
tions, the product may be damaged or destroyed.
Verify that the operating pressure in the interstitial space of the tank corre-
sponds to the operating pressure specified in the technical data of these
operating instructions.
Failure to follow these instructions can result in equipment damage.
 Verify that the product has been properly mounted.
 Verify that the product has been properly connected electrically.
 Verify that both valves are in the position "Normal Operation".
 Verify that the tightness test of the interstitial space has been properly per-
formed.
 Verify that the vacuum in the interstitial space has been reduced to
-420 mbar.
 Verify that the product is connected to the interstitial space.
 Verify that a liquid barrier has been installed.
 Verify that the housing of the product has been closed.
1. Apply voltage via the on-site mains fuse.
- The green LED is on.
- The pump controller keeps the operating vacuum constant. Once the
set vacuum is reached, the pump of the product switches off.
- The system is now ready for operation.
2. Have a specialised company certify the installation, commissioning and
test of the leak detector, see "Certificate of expert").