C e n t r a l C o n n e c t i o n U n i t P a n e l I n s t a l l a t i o n
20 Connect the light switch connections, connect
transformer to power supply.
Immediately check whether both halogen lights
operate correctly by pressing the light button.
21 Connect hand shower supply line with panel connection.
22 Pull sealing tape over top part of the panel.
23 Tighten central connection unit panel provisionally
with 2 tapping screws 4.8 x 32 (i and h).
24 Loosen screw f. Seal the points on the left and right
where the rubber sealing tape and the body pieces touch on
both sides with silicone free from acetic acid. Ensure that
some silicone is also applied just above and below
the rubber sealing tape as well
(approx. 10 – 15 mm):
Seal on both sides
with silicone free
from acetic acid.
Aktiva A8 hand shower
Attention: Adjust the panel flush to the
inner arch piece with panel screw g:
25 Inner arch piece: Tighten screw f. Then adapt the
panel to the inner arch piece by tightening screw g
(see figures on the right).
f
approx. 10 - 15 mm
approx. 10 - 15 mm
g
g
h
Correct:
Inner arch piece
Screw g of panel
tightened correctly:
Panel and inner arch
piece touch, this
avoids a gap
which leaks.
g
Panel
f
Light switch
connections
Light button
Hand shower
supply line
Panel
connection
Wrong:
Inner arch piece
Screw g of panel
too tight:
This creates a gap
underneath the
inner arch piece
which leaks.
g
Panel
65