Figure 1-2. VersaRails Rack Kit Contents
slide assemblies (2)

Installation Tasks

Installing a rack kit involves performing the following tasks in their numbered order:
1

Removing the rack doors

2
Marking the rack (if necessary)
3
Installing the slide assemblies in the rack:
RapidRails installation
VersaRails installation
4
Installing the system in the rack
5

Installing the cable-management arm

6
Routing cables
7
Replacing the rack doors
Removing the Rack Doors
See the procedures for removing doors in the documentation provided with your rack cabinet.
CAUTION:
Because of the size and weight of the rack cabinet doors, never attempt to remove or install
them by yourself.
CAUTION:
Store the two doors where they will not injure someone if the doors accidently fall over.
cable-management arm
10-32 x 0.5-inch
flange-head
Phillips screw (8)
status indicator cable (if applicable)
Rack Installation Guide