Herunterladen Diese Seite drucken

Ingeteam INGECON SUN STORAGE 100TL Handbuch Für Montage Und Betrieb Seite 92

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 5
Ingeteam
8.3. Terminal requirements for the AC connection
To ensure a correct connection, the terminals for M12 must meet the dimensional requirements below.
8.4. AC connection process
INFO
The unit is equipped with different cable entry systems to facilitate the installation with any cable section
chosen by the installer.
1.
Access the lower compartment of the inverter.
2.
Remove the polycarbonate guard.
3.
The elements to use vary depending on the cable diameter. The possible cases are explained below.
Option 1. Cable diameter 12 ~ 20 mm: cables pass through M40 packing gland
Remove the cable grommet membrane and install a M40 packing gland (supplied with the unit). Ensure
that the packing gland is fitted with a reducer that allows to maintain the seal in this range of cable
diameters. Fit the packing gland in the unit and pass the cable with its terminal through it.
Option 2. Cable diameter 20 ~ 28 mm: cables pass through M40 cable grommet membrane
Use the cable grommet membrane fitted as standard in the AC cable accesses. Fit the spade on the
cable. Insert the cable with its terminal through the membrane in the unit. For this operation we can use
a soapy solution. The cable itself will help to remove the plug in the membrane. Place the terminal in its
terminal block.
92
A ≤ 40 mm
13 ≤ B ≤ 15.5 mm
C ≤ 22 mm
D ≥ 13 mm
ABS2014IQM01_A - Installation and Operation Manual
AC connection