14
OPERATION
Secure the working environment before you start working.
Do not put the machine into operation before having read and understood the operation and
security guidelines as well as having performed all necessary checks and actions before first
operation.
Proper preparation and consistency of the concrete are essential for a good working.
Transport of the machine onto the concrete to be processed: Mount the transport bar into the
bar holder at the front side of the machine. Minimum two persons lift the machine onto the
concrete surface. Attention! The machine is heavy. Be sure to proper lifting technique to
avoid injuries.
Main switch ON
Cable pull starter
14.1.1 Shut off
Adjust rotors to even 0° position
Bring gas lever in position idle run position . Let the machine run for 1-2 minutes
Shut the machine off with main switch. NOW you close fuel cock lever
14.1.2 Starting with warm motor
Main switch ON
Open fuel cock
No choke when starting
ZIPPER MASCHINEN GmbH
BETONGLÄTTER / POWER TROWEL
Fuel cock open
Let the machine run in idle
run for 5 Minutes – then
Choke back
www.Zipper-Maschinen.at
ZI-MOS145Gite 23
OPERATION
Choker left
Adjust rotor blades
Seite 23