Commissioning

Explosion hazard due to incorrect installation!
Non-compliance results in severe or fatal injuries.
• Check the device for proper installation before commissioning.
• Comply with national regulations.
Damage or destruction of the device by arc and high pressure is
possible if improper switching operations are used!
Non-compliance can result in severe or fatal injuries.
• Quickly switch the device on and off completely.
• Avoid switching positions between 0 and I (ON and OFF).
Before commissioning, ensure the following:
• Monitor the mounting and installation.
• Enclosure must not be damaged.
• Remove any foreign objects.
• If necessary, clean the connection chamber.
• Check if all screws and nuts have been tightened firmly.
• Check if all conductors have been clamped firmly.
• Observe the line voltage.
9

Operation

The flange socket may only be operated when fully mounted.
The flange socket can only be switched with the plug inserted.
If the plug has been disconnected, lock the hinged cover with the
bayonet ring.
Only type 8570/12 and 8575/12 plugs from R. STAHL may be used.
When plugged in, the degree of protection of the 8575/12 plug is reduced to IP55.
271614 / 8570642300
2020-02-06·BA00·III·en·00
DANGER
WARNING
SolConeX Flange Socket, 16 A
Series 8570/15
Commissioning
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
EN
19

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis