Commissioning
6.1
Commissioning the product
Verify that the product has been properly mounted and electrically con-
nected.
UNINTENDED EQUIPMENT OPERATION
When the product is commissioned for the first time, the factory settings of the
product may cause switching of the outputs. This may result in unintended oper-
ation of connected equipment if the outputs are already wired when the product
is commissioned, for example, unintended starting of pumps or other system
components.
•
Only wire the analogue outputs and the relay outputs after you have
parameterised the product and after you have verified by means of a test
of the parameterisation that the system components to be connected
cannot cause hazards.
•
Before wiring the analogue outputs and the relay outputs, verify that
applying the supply voltage cannot cause unintended operation of con-
nected equipment.
Failure to follow these instructions can result in death, serious injury or
equipment damage.
Commissioning
WARNING
DA 10/12/14
EN
17