1. Remove screws at table insert. If required, turn ro-
tary table and incline saw head to be able to reach
the screws.
2. Remove table insert.
3. Install new table insert.
4. Tighten the screws at table insert.
Brush inspection
Check the carbon brushes after the first 50 operat-
ing hours with a new machine, or when new brushes
have been fitted. After carrying out the first check,
repeat the check every 10 operating hours.
If the carbon is worn to a length of 6 mm, or if the
spring or contact wire are burned or damaged, it is
necessary to replace both brushes. If the brushes are
found to be usable following removal, it is possible to
reinstall them.
When servicing the carbon brushes, open the two
latches counterclockwise (as shown in Figure 21).
Then remove the carbon brushes.
Replace the carbon brushes in the reverse order.
11. Storage
Store the device and its accessories in a dark, dry
and frost-proof place that is inaccessible to children.
The optimum storage temperature is between 5 and
30˚C.
Store the electrical tool in its original packaging.
Cover the electrical tool in order to protect it from dust
and moisture.
Store the operating manual with the electrical tool.
12. Electrical connection
The electrical motor installed is connected and
ready for operation. The connection complies
with the applicable VDE and DIN provisions.
The customer's mains connection as well as
the extension cable used must also comply with
these regulations.
• The product meets the requirements of EN 61000-
3-11 and is subject to special connection condi-
tions. This means that use of the product at any
freely selectable connection point is not allowed.
• Given unfavourable conditions in the power supply
the product can cause the voltage to fluctuate tem-
porarily.
• The product is intended solely for use at connec-
tion points that
a) do not exceed a maximum permitted supply im-
pedance "Z" (Zmax = 0.382 Ω), or
b) have a continuous current-carrying capacity of the
mains of at least 100 A per phase.
• As the user, you are required to ensure, in consulta-
tion with your electric power company if necessary,
33 | GB
www.scheppach.com /
service@scheppach.com /
that the connection point at which you wish to oper-
ate the product meets one of the two requirements,
a) or b), named above.
Important information
In the event of an overloading the motor will switch
itself off. After a cool-down period (time varies) the
motor can be switched back on again.
Damaged electrical connection cable.
The insulation on electrical connection cables is of-
ten damaged.
This may have the following causes:
• Passage points, where connection cables are
passed through windows or doors.
• Kinks where the connection cable has been im-
properly fastened or routed.
• Places where the connection cables have been cut
due to being driven over.
• Insulation damage due to being ripped out of the
wall outlet.
• Cracks due to the insulation ageing.
Such damaged electrical connection cables must not
be used and are life-threatening due to the insulation
damage.
Check the electrical connection cables for damage
regularly. Make sure that the connection cable does
not hang on the power network during the inspection.
Electrical connection cables must comply with the
applicable VDE and DIN provisions. Only use con-
nection cables with the marking „H05VV-F".
The printing of the type designation on the connec-
tion cable is mandatory.
AC motor:
The mains voltage must be 220 - 240 V ~ .
• Extension cables up to 25 m long must have a
cross-section of 1.5 mm
2
Connections and repairs of electrical equipment may
only be carried out by an electrician.
Please provide the following information in the event
of any enquiries:
• Type of current for the motor
• Machine data - type plate