Herunterladen Inhalt Inhalt Diese Seite drucken

Faults - WIKA 432.50.100 Betriebsanleitung

Vorschau ausblenden Andere Handbücher für 432.50.100:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

6. Commissioning, operation / 7. Faults
With filled versions the vent valve at the top of the case must be opened before
commissioning!
Commissioning of pressure compensating valve
Instruments which are fitted with a pressure compen-
EN
sating valve must, following installation, be vented for
internal pressure compensation.
Tool: Open-ended spanner SW 9
1. Remove plastic cap
2. Loosen the threaded connection above the valve
body
3. Screw the valve body tight, turned through 180°, with ≤ 4.5 Nm
For outdoor applications, the selected installation location has to be suitable
for the specified ingress protection, so that the instrument is not exposed to
impermissible weather conditions. For information on the ingress protection,
see Technical information IN 00.18
To ensure that the pressure can be safely vented in the case of failure,
instruments with blow-out device or blow-out back must keep a minimum
distance of 20 mm from each object.
Commissioning
During the commissioning process pressure surges must be avoided at all costs.
Open the shut-off valves slowly.

7. Faults

Personnel: Skilled personnel
CAUTION!
Physical injuries and damage to property and the environment
If faults cannot be eliminated by means of the listed measures, the
instrument must be taken out of operation immediately.
For contact details see chapter 1 "General information".
18
Ensure that there is no longer any pressure present and protect
against being put into operation accidentally.
Contact the manufacturer.
If a return is needed, please follow the instructions given in
chapter 9.2 "Return".
WIKA operating instructions pressure gauge model 4 per ATEX
Before commissioning
After commissioning

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis