Initial commissioning

6.1

Removing transportation packaging

!
On removing the outer packaging of the refrigerant
cylinder, make sure the cylinder hoses do not come
into contact with the housing or the filter dryer.
1. Remove the cardboard box.
2. Remove the ACS 611 from the packaging pallet.
3. Check delivery
contents.
4. Check oil level of vacuum pump (sight glass).
i
Do not disconnect any electrical connections,
and only have internal components opened and
repaired by trained customer service personnel.
i
Contact customer service in the event of any
transportation damage (e.g. oil leakage).
6.2
Connecting the service hoses
Connect the service hoses included in the delivery to
the service quick-release coupling HP and LP.
!
The connected hose length is provided in the
parameters of the software to precisely calculate the
refrigerant quantity. For this reason, any change to
the hose length must be entered into the software
settings in the "HOSES LENGTH" menu (see Sect.
11.3).
6.3
Connecting oil bottles and UV dye
bottles
!
Do not exert excessive force when removing or
inserting the UV dye, fresh oil and used oil bottles,
as this could damage the scales.
i
Pay attention to the symbols on the service flap
showing the type of bottle.
!
Only use dyes that have been approved by Bosch.
Non-approved dyes can lead to problems due
to chemical incompatibility with the internal
components in ACS 611. In the event that non-
approved dyes are used, no warranty claims shall
be applicable.
1. Fill the fresh oil bottle with compressor oil.
2. Connect the fresh oil bottle to the top quick
release coupling.
Robert Bosch GmbH
Initial commissioning | ACS 611 | 45 |
3. Fill the UV dye bottle with UV contrast medium.
4. Connect the UV dye bottle to the middle quick
release coupling.
5. Connect the used oil bottle to the bottom quick
release coupling.
6.4
Switching on the ACS 611
!
The ACS 611 is designed for 230 volts, 50/60 Hz.
Observe the information on the ACS 611 rating
plate.
1. Stand the ACS 611 on a flat, vibration-proof
surface.
2. Actuate the brake to stop the ACS 611 rolling.
3. Connect the power supply cord to the power
supply.
4. Switch on the master switch.
 Conducting display test.
"
Date and time (start screen) are displayed.
6.5

Required settings

!
The following settings must be checked or changed
during initial commissioning.
i
All other settings as well as the factory settings can
be found in Section "Settings".
6.5.1

Setting the language

1. Call up start screen.
2. Press <3> and <Flush> simultaneously and release.
 The message
ENTER CODE 0000
2222
and confirm with E.
3. Enter code
4. Select "LANGUAGE" with o u and confirm with E.
 Available languages are displayed.
5. Select language with o u and confirm with E.
"
Language is set.
i
Return with <Stop>.
en
is displayed.
|
1 689 989 600