114 | Commissioning
Storage system | Installation manual
Procedure
1. Wait until the device has completed the check.
2. If Not connected is displayed in the window behind
a component, check the connections.
Connections between:
The battery converter and the EMS (V-CAN)
The string inverter and the EMS (V-CAN)
The energy meter and the RS485 connector on
the EMS
If present: The PV sensor and the CAN Open
connector on the EMS
3. Note the serial number, which you can use to log
into the manufacturer's web portal.
4. If Connected is displayed beside every component
(with the exception of the PV sensor, as this is
optional), press Next.
8.3:
The information window
The information window is confirmed.