Commissioning and functional check

Preparing commissioning
Flush the inlet and outlet pipes. Remove any building rubble and dirt from inside the tank.
Connect water supply if necessary.
Fill separator with cold water up to the static level (level of the outlet).
Have a general inspection carried out (during initial commissioning and then every 5 years).
Give safety instruction.
File all records in the log book and document required disposal cycle.
All documents must be kept available at the system. The local supervisory authority can ask to examine the documents.