Installation requirements

The tumble dryer must only be installed and commissioned by Miele Customer Service
Department or an authorised dealer.
The tumble dryer must be installed in accordance with all relevant regulations and
standards.
The dryer must only be operated in a room that has sufficient ventilation and which is
frost-free.

General operating conditions

This dryer is intended only for use in a commercial environment and must only be oper-
ated indoors.
Do not install the tumble dryer in a room where there is a risk of frost.
Depending on the nature of the installation site, sound emissions and vibrations may oc-
cur.
Tip: Have the installation site inspected and seek the advice of a professional in instances
where increased noise may cause a nuisance.

Transport

The tumble dryer must not be transported without a transport pallet.
Suitable transport aids must always be used during transportation.
At the installation site, the tumble dryer must be lifted from the transport pallet using suit-
able lifting gear.

Installing the tumble dryer

Place the tumble dryer on a perfectly level, secure and horizontal surface that is able to
withstand the specified floor load.
The floor load created by the tumble dryer is concentrated and transferred to the installa-
tion surface via the adjustable feet. A base is not required. However, an uneven floor sur-
face must be compensated for.