Controls
52
Instruction Manual – Verdanium Home – Ver. 2.2.1 – 04.2021
Control buttons
The Verdanium Home is controlled by using the
keypad. The following functions are available:
•
System activation
•
System deactivation
•
Check system operation time
•
Reset filter change interval
Display
The display shows various functions and opera-
ting status of the Verdanium Home:
•
Status of the system
•
Information about filter change
•
Rinsing times
•
Operating times
•
Error messages
Interface
The interface is used to update the software of
the Verdanium Home.
Please note that this interface is only to be
accessed by authorised service providers. Any
interference with the control system irrevocably
leads to the loss of warranty.
After installation, you must put the system into operation. Please select in the operation mode menu the
commissioning program (IB-Programm).
Navigate with the ( + ) or ( – ) buttons to select the operation mode, Press the
BETRIEBSART
Button
mit "+" / "-" Taste
auswählen
This operating mode (IB-Programm) assumes that the Verdanium Home is correctly connected. The water
inlet and the withdrawal tap must be open.
During the first phase of commissioning the Verdanium Home will rinse the pre-filters (Filter spülen).
Filter spülen
Automatic
ESC ←
030%
While rinsing the membranes (Membran spülen), the disinfectant is removed from the membrane and
drains into the wastewater tube connection.
During the last phase of commissioning, the Verdanium Home rinses the ultra-pure water side of the mem-
branes and the post-filters (Permeat spülen).
Permeat spülen
Automatic
ESC ←
060%
When the commissioning program (IB-Programm) is completed, and the withdrawal tap is open, the Verda-
nium Home changes automatically to permeate production (Permeatproduktion). Continue operating the
Verdanium Home for additional 7 - 10 minutes to flush out any remaining disinfectant residues, and check
that all connections are leak-proof.
The Verdanium Home is now ready for use.
Instruction Manual – Verdanium Home – Ver. 2.2.1 – 04.2021
First commissioning
OK-Button.
IB-PROGRAMM
ESC ←
→ OK
Membran spülen
ESC ←
090%
PERMEATPRODUKTION
Gerät in
Betrieb
ESC ←
53