Safety notes
Avoid danger due to damaged external transformer
connection cables. In the case of damage, the
external transformer connection cable must be
replaced by the manufacturer or his customer service
department or an equally qualified person.
• Installation is only possible in frost-free rooms.
• The plug power supply is only suitable for indoor use.
• The plug-in connectors must not be directly or indirectly
sprayed with water when cleaning.
• The voltage supply must be separately switchable.
Application
Can be used in conjunction with:
• pressurised storage heaters.
Use in conjunction with unpressurised storage heaters
(displacement water heaters) is not possible.
Technical Data
• Flow pressure:
min. 0.5 bar - recommended 1 - 5 bar
• Operating pressure:
• Test pressure:
If static pressures exceed 5 bar, a pressure-reducing
valve must be installed.
Avoid major pressure differences between
hot and cold water supply.
• Flow rate at 3 bar flow pressure:
• Hot water supply temperature:
Recommended (energy economy):
• Voltage supply:
(plug power supply 230 V AC/6 V DC)
• Power consumption:
• Radio frequency:
• Transmitter power:
• Emergency voltage supply: 6 V lithium battery (type CR-P2)
• Pre set panel battery:
3 V lithium battery (type CR 2032)
• Automatic safety shut-off
(factory setting):
• Type of protection:
• Battery indicator:
• Water connection:
Electrical test data
• Software class:
• Contamination class:
• Rated surge voltage:
• Temperature for ball impact test:
The test for electromagnetic compatibility (interference
emission test) was performed at the rated voltage
and rated current.
Approval and conformity
This product conforms to the requirements
of the relevant EU guidelines.
3
max. 10 bar
16 bar
approx. 12 l/min
max. 80 °C
60 °C
230 V AC, 50/60 Hz
9 VA
2.4332 GHz
< 0.05 mW
60 s
- Fitting
IP 66
- Plug power supply
IP 40
- Battery unit
IP 66
- Operating panel
IP 69K
- Pre set panel
IP 57
Symbol in the display
cold - right
hot - left
B
2
2500 V
100 °C
The conformity declarations can be obtained
from the following address:
GROHE Deutschland Vertriebs GmbH
Zur Porta 9
D-32457 Porta Westfalica
Installation
Grease O-rings with the special grease supplied
prior to installation.

Electrical installation

Electrical installation work must only
be performed by a qualified electrician. This
work must be carried out in accordance with
the regulations according to IEC 364-7-701-1984
(corresponding to VDE 0100 Part 701) as well
as all national and local regulations.
Install operating panel, see fold-out page II, Fig. [1].
Note the seat of the recess for the cable, see detail.
Install function unit and thermistor, see Figs. [2] and [3].
Install spout, see Fig. [4].
Attach battery unit, see Fig. [5].
Install pre set panel, see Figs. [6] and [7].
Insert batteries with correct polarity.
Install pop-up waste (65 807), see fold-out page I.
Seal plug-hole rim.
Connect voltage supply, see Fig. [9].
Settings during a power failure / when changing batteries
No settings saved by the user will be lost when changing
the batteries or in the event of a power failure.
Flush piping system prior and after installation of fitting
thoroughly (Consider EN 806)!
Connect fitting, see Figs. [8] and [9].
The cold water supply must be connected on the right,
hot water supply on the left.
If the connections are transposed, the water routes
can be swapped in setting mode under Calibrate.
Open hot and cold water supply and check connections
for watertightness.
Operation
Using the operating panel
Start/Stop button
Starts and stops the fitting at a preset temperature
(factory setting 38 °C) and full flow rate.
Pause button
Interrupts the flow of water (temperature arrow
on operating panel orange). The flow is resumed
by pressing the button again.
The fitting switches off automatically
after a preset time (factory setting 60 s).
Temperature
Increases (red arrow, left) or decreases
(blue arrow, right) the water temperature.
Volume
Increases
or decreases the flow rate
in four stages in total.