2.4.2 Installation stages of stations with separate resin tank and brine tank (simplex)
Stations with separate resin tank and brine tank are supplied in a semi-assembly condition. Their
assembly will be carried out on the mounting spot. For assembly you should carry out the following steps:
(See figure 6, page 6)
Set the system at the decided spot while observing the conditions under items 2.1 and 2.2.
(1) After positioning the resin tank (FRP), the central tube with the pre-mounted diffuser is mounted inside
in the lower part of the tank in the pre-defined position (it is usually mounted).
(2) The level in the upper part of the central tube with diffuser should be at the same level with the opening
of FRP tank, maximum accepted at +5mm.
(3), (4) Cover the central tube in the upper part.
(5) Fill FRP tank with the filtering agent. Make sure the filtering agent does not go also in the central tube.
While filling FRP tank with the filtering agent make sure that the central tube remains in vertical position
and inthe middle of the tank.
Take care!: do not extract the central tube with pre-mounted diffuser from the initial position.
(6) Remove the cover of the central tube.
(7) The resin tank (FRP) thread is cleaned off particles of the filtering agent (it may be cleansed with water).
(8) The upper diffuser (superior crib) is mounted on the valve, as such: inside the valve there are 4 fixing
wedges and on the crib 4 appropriate slots, they are to be coupled between them by pressing so as the
wedges to go inside the slots and then the crib is rotated. The mounting of the crib on the valve will be
checked while trying to extract the crib.
(9) The assembly of the control valve with mounted upper diffuser is introduced on the central tube by
pressing. The upper diffuser mounted in the valve should coat the central tube.
(10) Screw the control valve to (FRP) resin tank.
(11) Lift the cover of the brine tank and introduce the tube through the existing inlet.
(12), (13) The nut of the brine elbow will be loosened from the valve, the tube is inserted through the nut
so as to go beyond for approximately 1 cm. The taper part is introduced in the tube.
(14) The assembly is screwed in the valve.
(15) The by-pass locks are taken out and the connectors are introduced through pressing.
(16) The by-pass locks are mounted.
(17) By-pass is introduced in the valve.
(18) The connection between the by-pass and the valve is assured by means of the metal clips.
(19) The output sensor is introduced in the by-pass.
(20) Complete system.
Observe further on the mounting steps (see 2.4.1) from the cabinet alternative.
Observe further on the steps for putting into operation from the cabinet alternative.