Herunterladen Inhalt Inhalt Diese Seite drucken

Chapter 3 Verifying The Installation - Dell PowerConnect W-6000 Installationsanleitung

Vorschau ausblenden Andere Handbücher für PowerConnect W-6000:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 34
Once the W-6000 controller is physically installed, run the following power-on test:
1. Turn on all installed power supplies in quick succession.
For each power supply, place the power switch in the on (|) position.
NOTE: To avoid overloading the first power supplies to be turned on, all required power supplies should be turned on at roughly
the same time (within about three seconds).
2. Check for the proper power indicators.
Immediately upon power up, you should observe the following:
All power supply AC OK and DC OK LEDs light solid green.
The fan tray Fan Status LED is solid green and you should be able to feel significant airflow blowing from
the chassis vents at each of the three fan positions.
3. Check for the appropriate operation indicators.
Once the system has successfully booted, you should observe the following:
The power supply AC OK and DC OK LEDs are still solid green.
The fan tray Fan Status LED is still solid green.
NOTE: For more information on LED behavior, refer to the individual chapters for the specific modules.
4. Once the system has passed the initial power-up test:
Connect appropriate network cables.
5. You are now ready to perform the initial setup as described in the Aruba Quick Start Guide (which is included
in the Accessory Kit) for the software loaded on your controller.
Dell PowerConnect W-6000 Controller | Installation Guide
Chapter 3
Verifying the Installation
Verifying the Installation | 15

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis