Set-up / Installation
3.4.2
Installation Layout Below the Water Level
Figure: horizontal installation
3.4.3
Connecting Heat Exchanger
• Install blocking and control units and drain valves in the flow pipes and return
pipes of the heating cycle within the frost-proof installation area.
The heat exchanger might be damaged.
Ensure observance of the water quality and of maximum pressures.
take care
The heat exchanger might be damaged.
When external cycles are connected, please take care that metal particles do not
enter the heat exchanger.
take care
Brass connections between the heat exchanger and steel pipes serve for electrical
separation.
The heat exchanger might be damaged by chemicals.
Disinfecting devices are always to be installed after the heat exchanger. If chemi-
cals (e. g. chlorine gas) are used, gases must not enter the heat exchanger during
take care
filter standstill times.
24
Figure: vertical installation