Commissioning / operation

5
Commissioning / operation
5.1

Start-up

Personnel:
Protective equipment:
NOTICE!
Before commissioning, check the resistance of the O-rings to the chemical to
be pumped:
– EPDM for alkaline
– FKM HF for sour
Fig. 3: Putting the suction lance into operation
1.
Mount a connection matching the suction connection of the pump on the 2'' thread of
the suction connection.
2.
If a product return is available, mount it with a suitable connection on the 2'' thread of
the return connection.
3.
Connect the empty signal reserve contact to the empty signal input connector.
MAN050418 Rev. 2-10.2023
n
Operator
n
Specialist
n
Protective eyewear
n
Chemical-resistant protective gloves
n
Safety shoes
1
2
3
4
NOTICE!
– Tighten the union nuts on the connections and the barrel screw
connection only hand-tight. Do not use any tools!
– Do not interchange the suction and return connections.
4 'Structure' on page 19
1
Empty signal input plug
2
Suction connection
3
Return connection
4
Barrel screw connection
20