MECHANICAL CHECK
PERFORM THE FOLLOWING OPERATIONS:
1. CLOSE THE "EMERGENCY" CIRCUIT-BREAKER, INSTALL SPRING "O" ON THE 1 AND 2 CIRCUITBREAKERS AND MAKE SURE THAT THE 1 AND 2 CIRCUITBREAKERS
CANNOT BE CLOSED. THEN OPEN THE "EMERGENCY" CIRCUIT-BREAKER.
2. CLOSE THE 1 AND 2 CIRCUIT-BREAKERS, INSTALL SPRING "O" ON THE "EMERGENCY" CIRCUITBREAKER AND MAKE SURE THAT THE "EMERGENCY"
CIRCUIT-BREAKER CANNOT BE CLOSED. THEN OPEN THE 1 AND 2 CIRCUIT-BREAKER.
3. CLOSE THE "EMERGENCY" CIRCUIT-BREAKER AND CHECK THAT THE 1 AND 2 CIRCUITBREAKERS CANNOT BE CLOSED. THEN OPEN THE "EMERGENCY"
CIRCUIT-BREAKER.
4. CLOSE THE 1 AND 2 CIRCUITBREAKERS AND CHECK THAT THE "EMERGENCY" CIRCUIT-BREAKER CANNOT BE CLOSED. THEN OPEN THE 1 AND 2 CIRCUITBREAKERS.
5. REPEAT THE STEP 3 AND 4 THREE TIMES, THEN CHECK THE ADJUSTMENTS AND THE FASTNESS OF THE TIE-RODS.
机械检查
执行下列操作:
1. 闭合"应急电源"断路器,将弹簧"O"分别安装在断路器1和2上,确保断路器1和2不能闭合。然后断开"应急电源"断路器。
2. 闭合断路器1和2,将弹簧"O"安装在"应急电源"断路器上,确保"应急电源"断路器不能闭合。然后断开断路器1和2。
3. 闭合"应急电源"断路器,检查断路器1和2应不能闭合。
4. 分别闭合断路器1和2,检查"应急电源"断路器应不能闭合。
5. 重复步骤3和4三次,然后检查拉杆的调整及牢度。