5.0 Storage and preservation

The purpose of this chapter is to specify how to handle and preserve a product from the
day of shipment until the equipment is installed and commissioned.
Following conditions shall be observed for the installation/construction period.
CAUTION
CAUTION
CAUTION

5.1 Preservation during the transportation and pre-installation period

The packaging provides both mechanical and environmental protection. If the equipment
is intended for service in an outdoor environment, to avoid any risk of harmful metallic dust
during storage it is protected with enveloping plastic foil.
All openings such as cable entry holes are adequately sealed.
Packages must not be opened, or their integrity disturbed during the transport.
Packing may only be opened when the equipment has been taken from storage and has
been transported to its intended location of installation, or to connect the anti-condensation
heater, after which the packing must be resealed. Storage preservation measures are
immediately invalidated as soon as the packaging is disturbed.
One shall inspect packages on receipt at the storage warehouse and at regular monthly
intervals during the storage period in regard to external damages. Any visible damage that
may have a consequence to the condition of the contents or integrity of the preservation
must be immediately documented and reported. In case of such an event, the supplier
must be contacted immediately for advice

5.2 Preservation during the installation/construction period

The product must be unpacked only when the equipment is to be installed, or to connect
the anti-condensation heater. It is recommended to maintain the integrity of the packaging
during transport from the storage warehouse to the installation site.
Inspect the equipment within each package for damage and condition as soon as the
package is opened. Report and document any damage immediately. In case of such an
event, the supplier must be contacted immediately for advice.
Installation and handling of the equipment once unpacked must be performed in
accordance with the relevant elements of the documentation for the equipment delivered.
During storage, prior to installation the unit must be
stored dry with a relative humidity <60 %, temperature
>15ºC.
Replace desiccant bag in junction boxes and enclosures
(if any) every 6 months.
Keep a log of the replacements as documentation.
The Anti condensation heater, if any, must be powered
up and connected at all time.