Making drillholes
Mark the 6 holes on the concrete foundation using the baseplate of the floor-mounted
column.
Make sure that the connection cable is located precisely underneath the opening in the
baseplate.
Drill the 6 mounting holes:
Diameter: 10 mm
Drill-hole depth: 33 mm
Hammer the enclosed dowels using the Hilti HSD-G manual setting tool (not included
in the scope of delivery) so that they are flush with the floor.
Hilti HSD-G manual setting tool. Source: Hilti
Please also observe the following instructions:
Instructions on inserting the dowels. Source: Hilti
Floor-mounted column from below
KeContact P20/P30 - Floor-mounted column, v2.40, #90333
© KEBA 2012-2016
Thread in cable
Thread the connection cables from the
bottom through the column upwards
through the cable opening.