6. Installation/Wiring work
(1) Installation work
Controller can be installed either in the switch box or directly on the wall. Perform
the installation properly according to the method.
1 Drill a hole in the wall.
Installation using a switch box
Drill a hole in the wall, and install the switch box on the wall.
Connect the switch box to the conduit tube.
Direct wall installation
Drill a hole in the wall, and thread the cable through it.
2 Seal the cable access hole with putty.
Installation using a switch box
Seal the remote controller cable access hole at the connection of switch
box and conduit tube with putty.
To reduce the risk of electric shock, malfunctions, or fire, seal the
gap between the cables and cable access holes with putty.
3 Prepare the bottom case of the remote controller.
4 Connect the remote controller cable to the terminal block on the bottom case.
4
Peel off 6 mm of the remote controller cable sheath as shown in the figure below, and thread the cable from behind the bottom
case. Thread the cable to the front of the bottom case so that the peeled part of the cable cannot be seen behind the bottom
case. Connect the remote controller cable to the terminal block on the bottom case.
Thread the sheath part
of the cable to the front.
Sheath
10 (13/32)
Front
6 (1/4)
Thread the cable.
unit: mm(in)
Direct wall installation
Seal the hole through which the cable is threaded with putty.
To reduce the risk of electric shock, shorting, or malfunctions, keep
wire pieces and sheath shavings out of the terminal block.
Important
Do not use solderless terminals to connect cables to the terminal
block.
Solderless terminals may come in contact with the circuit board and
cause malfunctions or damage the controller cover.
Back
Bushing
Front cover and top case
2-core wire must not
be seen on the back.
Route the cable behind
the remote controller.
- 5 -
Conduit
Wall
tube
Locknut
Switch box
Seal the gap
with putty.
Remote
controller cable
Bottom case
Connect the cable.
(non-polarized)
Connect the cable
so that the cable
sheath is not
pinched.
Remote controller
cable
Seal the gap with putty.

Werbung