Installation Possibilities; Dimensions, Weights, Centres Of Gravity, Capacity; Installation Requirements; Mounting/Installation - RITZ Series RITZBloc Betriebsanleitung

Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

Series RITZBloc
2.4

Installation possibilities

2.5

Dimensions, weights, centres of gravity, capacity

Information on request.
For weights refer to the contract documentation.
2.6

Installation requirements

• Protect motors and pumps from the weather.
• Ensure that the workplace is adequately ventilated/heated/
cooled and observe noise protection requirements.
• Check that the transport / taking away of the pump set or its
components to / from installation site is possible without dan-
ger of accident.
Openings must be large enough.
• Adequately rated lifting equipment must be available.
2.6.1
Space required for operation and maintenance
• Ensure that sufficient space, at least from 2 sides, is left for
subsequent maintenance requirements. This space should
have, for reason of good accessibility, min. 0.8 m width.
• The set should be easily accessible from all sides.
• The motor cooling fan requires adequate clearance around
the cowl. Ensure that the air inlet and outlet areas are unob-
structed.
2.6.2
Foundations
• Concrete plinths must be adequately supported in order to
ensure installation safe and functional.
• Foundation length: min. 100 mm longer than the supporting
surface.
• Width: The fixing bolts should be at least 100 mm in front of
the edge of the foundation.
• The depth of the foundation should be sufficient to prevent
frost and to be on firm ground.
• Plinths which rest on a structural floor or ceiling should be in-
tegrated into the original construction using bridging rein-
forcement.
• Foundations should contain sufficient mass in order to damp-
en resonant vibrations.
2.6.3
Supply connections
Check that all supplies like power, water and drainage neces-
sary for installation and later operation are available in the form
required.

3. Mounting/installation

Care and attention to detail during installation are essen-
tial for a trouble-free operation. Incorrect procedures dur-
ing installation may create hazards for personnel or
property or lead to premature failure of the pump.
3.1

Preliminary checks

Check that the dimensions of the plinth/foundation are in ac-
cordance with the drawings.
3.2

Installation

This pump arrangement may be installed on a plinth, concrete
foundation, structured steelwork or directly in the pipeline, de-
pending upon pump size and local conditions.
3.2.1
Pumps with disc coupling (B)
• The pump set should be mounted and aligned as per para.
3.2.
Pumps supplied without motor:
Pumps without mounted motor are delivered with an assembly
accessory implement which prevents a movement of the shaft
resulting possibly in smashing the mechanical seal. The as-
sembly accessory implement may not be removed until the
pump shaft is firmly connected with the motor shaft. For this,
please proceed as follows:
• Place the motor-side coupling half on the motor shaft. Align
axially. Observe setting dimensions (see table 2 for toleranc-
es).
• Spot-drill the motor shaft through thread of coupling half
(depth and diameter of drilling corresponding to the set screw
dog point).
• Screw in set screw with dog point and tighten well.
• Mount motor on drive lantern and bring the two coupling disc
halves into line.
• Tighten connecting screws of the disc coupling and drive lan-
tern (tightening moment for connection screws of coupling
halves see table 1). The disc coupling nuts are to be secured
by sticking.
Thread [mm]
M8
M12
M16
Table 1: Tightening moment for coupling screws
Tightening moment [NM]
36
125
305
15