TEST RUN

Before test run

• Before turning on the power supply, carry out the following procedure.
1) Using 500V-megger, check 1MΩ or more exists between the terminal block 1 to 3 and the earth.
If 1MΩ or less is detected, do not run the unit. Do not apply to the remote controller circuit.
2) Check the valve of the outdoor unit being opened fully.
• To protect the compressor at activation time, leave power-ON for 12 hours or more be for operating.
How to execute a test run
Using the remote controller, operate the unit as usual.
For the procedure of the operation, refer to the attached Owner's Manual.
A forced test run can be executed in the following procedure if the operation stops by thermo.-OFF.
(This method is limited to when wired remote controller is installed.)
In order to prevent a serial operation, the forced test run is released after 60 minutes have passed and returns to
the usual operation.
When the remote controller is used for the first time, it accepts an operation approx. 5 minutes after the power
supply has been turned on.
It is not a trouble, but is because the setup of the remote controller is being checked.
For the second power-ON time and after, approx. 1 minute is required to start the operation by the remote
controller.
Do not use the forced test run for cases other than the test run because it applies an excessive load to the
devices.
CAUTION
NOTE