Herunterladen Diese Seite drucken

Werbung

4B. coNNectING the SePaRate
elemeNtS
Lift the assembled structure onto the prepared
steel base and connect loosely using clips
(9002) (4.7).
Loosely connect the door runner bar (2062) to
steel base lengths (9142) and (9143) using
bolts (2007) inserted into the (2062) bolt chan-
nel (4.8) (4.9). The nuts (1002), inside the
base, will be tightened after the doors have
been positioned in section 5 (5.9).
Connect the roof glazing bars (2055) between
the eaves (4.10) and the ridge bar (4.11). In-
sert extra bolts into each glazing bar depen-
ding on which house you have bought. The
number is indicated in a circle on each bar and
to be read beginning from both ends.
The corner braces (2056) (4.10), the roof
braces (2057) (4.12) and the cross braces
(2033) (4.14) (4.15) (4.16) can now be con-
nected.
Please do not over tighten. (max. 3Nm)
Adjust the greenhouse until it is completely
square and tighten all bolts.
Please do not over tighten.
Press the end protectors (1017) and (1018)
onto the profile ends (4.13).
5l and 5R. DooRS
attention: Do not stand the assembled
doors on the door gliders (1014) to avoid
damaging them.
Push the door gliders (1014) onto both ends of
door bar (1360) (5.1).
Assemble the doors as shown in diagram 5.
Bolt door bar (1362) to upper bar (1359) (5.3)
and slide door seals (5021) into door bars
(2063) (5.5). Slide bolts (1500) into the bottom
of the bolt channel holding brush seals (5021)
and fix it in place using nut (1515) (5.6). Cut
the door seals (5021) to length. Please ensure
that for the inside side bar the part (2065) is
used on the left in (5L) and (2064) on the right
in (5R).
Connect door rollers (1015) to the door bar
(1362) using bolt (1304), washer (1009) and
nut (1007) (5.4).
Connect bolt (2001) at the join between both
(1347) as shown (5R).
Loosen the door supports (2043).
Now slide the door rollers into the door runner
bar (1347) (5.7). Please ensure that the door
gliders are also running on the bottom track
(2062) (5.8).
060.01.1511
Reconnect door supports (2043).
Tighten the nuts (1002) on bolts (2007) to pull
(2062) tight against the base lengths (5.9).
Adjust the door so that it moves freely.
6. Roof veNtS
Connect the side bars (1065) and the top bar
(1064) depending on the pane thickness.
Up to 4 mm, see (6.1). For 4 mm and over,
see (6.2).
Place the bolts to connect the bottom bar
(1066) in the prepared holes, and then slide
the glass into the tracks in side bars (1065)
(6.3).
Now connect bottom bar (1066), and ensure
that the window is totally square before tighte-
ning all bolts.
Position the window in the ridge bar from one
end (6.4) and (6.5) and slide it to the required
position (6.6).
Connect the window sill (1063) with the extra
bolts in the roof bars (6.7).
Connect the window opener (1067) to the bot-
tom bar (1066) using screws (1006) (6.8).
Place the plastic cap (1019) over the end of
the window opener (6.6) and connect both
window fixers (2016) onto the window sill
(1063) using screws (1006) (6.8).
7a. 7B. 7D. GlazING – GlaSS / Pc
Please note the already mentioned safety
precautions.
Important! The UV-resistant side of
Polycarbonate (PC) sheets is indicated by the
plastic film and printing at the edge. this side
must face outside.
Remove the film. Note! Completely remove
the film only after the sheet has been
positioned in the greenhouse. (The sheets are
cut marginally shorter to allow for expansion in
warm conditions).
Press the glazing seals (1020) onto the
aluminium profiles (7.2) and cut to length.
Fix the glass panes and PC sheets in place
using the glazing spring clips (1011) (7.1) and
note the quantity required on each pane.
In order to give the Polycarbonate sheets extra
stability, connect them to the aluminium
profiles, in the middle of each sheet, with a Z
profile (7.3 - 7.8) and at the ridge by pushing
spacer (2399) onto the ridge bar (7.5).
7c. GlazING – GlaSS
Please note the already mentioned safety
precautions.
Press the glazing seals (1020) onto the alumi-
nium profiles (7.2) and cut to length.
On the roof begin by positioning the glass at
the eave and fix in place using the glazing
spring clips (1011) (7.1). The following pane
should be placed over the pane directly under
it and held in place with the glass retaining
clips (1012) between the panes (7.9).
On the sides please begin from the bottom.
fINIShING
Fill the holes for the anchor legs with concrete.
The steel base should be connected to the
foundation using screws and plugs (not provi-
ded).
If desired, it is possible to seal the greenhouse
at the edges using neutral silicone. Silicone is
not in cluded.
Place the warning label inside the house.
A full range of accessories is available to help
you make the most of this product. Please
contact your local stockist for details.

Safety NotIce

In the event of high winds, close all doors and
vents.
In the event of heavy snowfall, clear the roof
of the building or take suitable measures to
support the roof. Heat the building in winter.
commeNtS
For the complete protection of your new
greenhouse, we advise you to include it in
your house insurance. Please take note of
possible building rules relating to the position-
ing of greenhouses.
Please stick the greenhouse model label pro-
vided onto the door bar (1362) after success-
fully assembling this product. This information
is important in the event that replacement
parts are later required.
Please keep these Assembly Instructions in
a safe place, for future reference!
Our policy is one of continuous improvement
and we reserve the right to change the specifi-
cations without prior notice.