Electrical Connection and Fitting to The Tower
1. Run the cable selected (see Table 1) down the inside of the pole.
2. Select one of the 2 basic wiring systems on page 12 and follow the manual
provided with the voltage controller.
3. Connect the wind generator flying leads to the cable protruding from the
tower using the connector block supplied, taking care to observe polarity.
Connect the Windcharger + to cable + and windcharger – to cable –
Red is
+ Positive
Black is - Negative
4. Wrap the connection with insulation tape to secure/protect from environment.
Alternatively join the cables using a latching-type plug and socket.
5. Locate the wind generator into the tower whilst gently easing the cable from
the tower base to ensure the cable is not trapped. Secure the wind generator
to the tower using the button cap screws and shake proof washers provided,
tighten using the 6mm Allen key provided.
Up and Running
Four Point Final Checklist
Before raising and securing the wind generator:
1. Check the tightness of the blade & tail fixing screws and generator mounting
screws.
2. Check free rotation of the hub and yaw axis.
3. Check that the cable is not trapped.
4. Check that all electrical connections are secure and safe.
The wind generator can now be raised into position.
Take care to avoid all moving parts when raising and lowering the wind
generator.
When raised, secure the structure firmly in an upright position.
Caution-The performance of your Windcharger will be impaired if the pole is
not vertical.
Doc No:SM-137 Iss. C 13.02.13
11
Installation & Operation
Marlec Eng Co Ltd

Werbung

Inhaltsverzeichnis
loading

Verwandte Produkte für Marlec Rutland 914i Windcharger

Inhaltsverzeichnis