4.2.4 Work steps

2.
4.
1. Remove insulation shells
2. Plug hollow plug of the power pack into the socket
3. Lead cable of alarm signal through the strain relief device (optional)
4. Lead cable of power pack through the strain relief device
5. Carefully re-attach insulation shell halves
- The cables have to lie in the section provided for them, and the insulation
shells must be fitted without a gap (the right and left insulation shell
halves fit onto the tap in only one direction)
Honeywell GmbH
GB

5. Start-up

Performance of tasks only by qualified personnel (see section 1.6).

5.1 Safety instructions for start-up

Warning
3.
Inform yourself sufficiently about
• the tap's equipment
• the way the tap functions
• the immediate environment of the tap
• the measures to be taken in an emergency

5.2 Initial operation

The tap was set in the factory and after installation and completion of all
preparations can be put through a trial run to check its functioning.
1. Switch on main switch of the power supply
2. Plug in power pack
- only use moisture -proof socket (IP54)
3. Check screw fittings for impermeability
18
Danger from improper operation.
Malfunctions
Prior to start-up, the operating manual of the operator and of the
specialist personnel/operating company in charge are to be
read and must be permanently accessible on site of the tap or
the system.
The local safety and accident regulations are to be observed
when starting up the tap.
Damaged or wrongly installed tap.
Malfunctions
Check the tap for visible damage; eliminate any defects at once
or report to the supervising personnel. The tap may only be
operated when in perfect working condition.