Configuration

For the individual configuration of a instrument with standard configuration the
instrument must be connected to a PC via the USB infrared cable (order no.
83 17 409) or the E-Cal system. The PC software "Dräger CC-Vision" is used to
perform the configuration.
Changing the configuration: see the Technical Handbook.
Standard instrument configuration:
Dräger X-am 5600
1)
Bump Test Mode
1)2)
Clean air adjustment
3)
Hydrogen added signal
1)
Life sign
1)
Off
1)
LEL factor
4.4 vol. % (4.4 vol. % corresponds to 100 %LEL)
ch
4
4.0 vol. % (4.0 vol. % corresponds to 100 %LEL)
H
2
1)
Averaging time
1)
Different settings can be selected to meet customer requirements on delivery. The current
setting can be checked and changed with the Dräger CC Vision PC software.
2)
Fresh air calibration / zero point adjustment is not supported by the DrägerSensor DUAL IR CO
the DrägerSensor IR CO
or the DrägerSensor XXS O
2
3)
In the case of activated DrägerSensor XXS H
DrägerSensor DUAL IR Ex/CO
(68 11 960) or DrägerSensor IR Ex (68 12 180).
2
By activating the H
added signal, the LEL gas concentration of the activated
2
DrägerSensor XXS H
HC (68 12 025) is added to the LEL gas concentration of
2
the activated DrägerSensor DUAL IR Ex/CO
DrägerSensor IR Ex (68 12 180) and shown on the display at the position of the
IR Ex display.
Previously set alarm thresholds are preserved so that in the presence of
hydrogen (H
) the alarm of the IR Ex channel could be triggered earlier.
2
16
Quick bump test
on
on
on
disabled for A2
15 minutes for STEL
8 hours for TWA
.
3
HC (68 12 025) and activated Ex Channel in the
2
(68 11 960) or of the activated
2
NOTICE

First commissioning

Before using the instrument for the first time, insert the batteries supplied or
a charged NiMH power pack T4 (order no. 83 18 704) / T4 HC (order no.
83 22 244) (see "Replacing the batteries / rechargeable batteries" on
page 19).
The Dräger X-am 5600 is ready for operation.
Operation
Switching on the instrument
Press and hold the [ OK ] key for approx. 3 seconds until the countdown
» 3 . 2 . 1 « shown in the display has expired.
All the display segments, including the visual, audible and vibration alarms,
are activated for a short time.
The software version is displayed.
The instrument performs a self test.
The next sensor to be calibrated/adjusted is displayed, along with the
remaining days to the next calibration /adjustment, e.g.
» ch
%LEL CAL 123 «.
4
The time until the bump test interval elapses is displayed in days, e.g.
» bt 2 «.
,
2
All alarm thresholds A1 and A2 as well as »
1)
(STEL)
, if required, are displayed consecutively.
During the running-in period of the sensors, the respective display of the
measured value flashes and the special symbol»
displayed. No alarms are issued during the running-in period of the sensors.
Press the [ OK ] key to cancel the display of the activation sequence.
Switching off the instrument
Press and hold the [ OK ] key and the [ + ] key simultaneously until the
countdown » 3 . 2 . 1 « shown in the display has elapsed.
Before the instrument is switched off, the visual, audible and vibration
alarms are activated for a short time.
1)
Only when activated in the instrument configuration. Delivery status: not activated.
1)
« (TWA)
and »
«
« (for warning) is