2.8.1.
Three phase installation
In the case of three-phase installation, follow the steps below:
1.
Loosen the left-hand box sheath (P) and insert the Ø 25 mm corrugated sheath.
2.
Tighten the box sheath (P).
3.
Insert the power supply cables and connect phases, the neutral N and the earthing
cable PE to the CN1 power supply terminal block, making sure that the entire stripped
section of each cable is fully inserted into each terminal.
To configure the maximum current phase unbalance, enable the load unbalance
function through the Modbus Map. This configuration is mandatory in the following
countries:
• Germany
• Austria
• Switzerland
For further details, check the dedicated manual on eSolutions website
www.esolutions.free2move.com/document-library/
281