12.1
Fittings
Remove the lifting eyes before commis-
sioning.
Remove the transportation immobilisers
and spacers.
Return parts that can be reused to the
manufacturer or supplier.
This installation manual must be given to the customer and kept safely during the entire period of use!
12.2
Functional test
Levellers are tested and delivered including
the hydraulic oil.
The following must be taken into considera-
tion during commissioning:
Check that the leveller platform and
the loading bay floor are at the same
height.
12. Commissioning
Make sure that the operators receive
instruction.
Perform a trial run.
When doing so, refer to the separate
manual for the controls.
Check that the leveller operates
smoothly and without excessive noise.
Have the safety features tested.