Mounting Schüco modules
The modules have been evaluated for a maximum positive or
negative design load as follows:
snow 5400 Pa
wind 2400 Pa
Two mounting approaches are commonly employed:
Stand-off Method:
The modules are supported parallel to the surface of the
building wall or roof. Clearance between the module frames
and surface of the wall or roof may be required to prevent
damage to the wiring or junction box and is recommended to
allow air to circulate behind the module. The recommended
stand-off height is 115 mm.
Rack Method:
The supporting frame is used to mount modules at the proper
tilt angles. The modules are not designed for integral mounting
as part of a roof or wall. The mounting design may have an
impact on the fire resistance.
11.2011
Installation and electrical connection
The necessary electrical connections to the
main power grid may only be performed by a
qualified electrician.
90°
Observe the electrical ratings of all the equipment in the
system.
Beside the Junction box with integrated bypass diodes, the
module is equipped with MC-T4 plugs and sockets or 100%
compatible plugs and sockets.
The plug-in connections must be fully fitted and
secured.
Fix the cable on the module frame or installation system.
Only MC-T4 compatible plug-in connectors and special solar
cables can be used to lengthen the module connector cables.
These have to meet the electrical requirements of the designed
interconnection.
Under certain conditions, a photovoltaic
module is likely to produce more current
and / or voltage than reported at standard
test conditions. Accordingly the values of
I
SC
be multiplied by a factor of 1,25 when
determining component voltage ratings,
conductor current ratings, fuse sizes, and
size of controls connected to the PV output.
232 598
DANGER
Do not expose the module to
sunlight during installation;
cover the front of the module
with opaque material.
Ensure module is aligned in the
best available tilt and oriention.
IMPORTANT
and U
marked on this module should
OC
EN
15

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Mpe 370 mp05Mpe 375 mp05Mpe 380 mp05

Inhaltsverzeichnis