5.10.5
Securing the flue system
IMPORTANT
These regulations are typical for both concentric and parallel flue
systems.
The flue system must be secured to a solid structure.
The flue system should have a continuous fall back to the boiler (1.5° to
3°). N.B. Wall terminals must be installed leveled..
Only use accompanying brackets.
Every elbow must be secured by using the bracket.
Exception at connecting on boiler:If the lenght of the pipes before and after
the first elbow, are no more than 250 mm, the second element after the
first elbow has to contain a bracket.
Note: The bracket must be positioned on the elbow!
Every extension must be secured per metre with a bracket.
This bracket must not be clamped around the pipe ensuring free
movement of the pipe..
Make sure bracket is locked into the correct position depending on the
position of the bracket on the pipe or elbow:
Do not mix flue parts or clamps of different suppliers.
Max. distance between clamps
Vertical
Others
2000 mm
1000 mm
Divide the lengths between the brackets evenly.
Every system must contain at least 1 bracket.
Position the first clam at a maximum of 500 mm from the boiler.