UNPACKING INSTRUCTIONS

Before assembling the ceiling fan, remove all parts from the shipping carton and check them against
the parts listed below (Fig. 1 ) :
A-
Support plate (1 pc.)
B- Motor assembly and support (1 pc.)
C- Blades (3 pcs.)
D- Blade fitting screw (6 pcs.)
E- Washers (6 pcs.)
F- Speed regulator (1 pc.)
G- Wall plugs (2 pcs.)
H- Screws (2 pcs.)
I-
Washers ( 2 pcs.)
J- Felt washers ( 3pcs )
Instructions Manual

INSTALLATION INSTRUCTION

FITTING THE FAN TO THE CEILING
Important: To avoid the possibility of accidents caused by the fan, which could imply legal
responsibilities for the installer, compliance with each of the following instructions is essential.
Ensure that the distance between the lowest point of the fan, once installed, and the floor is at least
2.3 metres.
Check that the means of fitting the fan to the ceiling is capable of supporting the weight of the fan
when in operation. (HTB 75 N / HTB 90 N Minimum 25 Kg. - HTB 150 N Minimum 40 Kg. ).
Fitting to a concrete ceiling
To ensure correct installation, drill four holes of the same diameter as the wall plugs (G) in the
concrete ceiling. Insert the plugs supplied and fix the support plate (A) using the four screws (H)
and washers (I) provided. (Fig.2).
Fitting to a false ceiling
Make a hole in the false ceiling that is large enough to allow the introduction of a rigid, wooden or
metal cross beam. This should be as long as possible and under no circumstances less than 25cm.
in length, to allow the best distribution of the weight of the fan.
Without reducing its ability to support the fan, make a small groove at the centre of the crossbeam,
then locate the beam so that its centre coincides with the hole in the ceiling.
Join the support plate (A) to the crossbeam using galvanised metal wire of at least 2.5mm in diameter.
Passing the wire through the grooves in the plate, wind it around the crossbeam and back through
the plate a minimum of six times, so that at least some of the turns pass through the groove in the
crossbeam. Secure the wire by twisting it around itself several times.
Ensure that the ceiling is able to support the weight of the fan when in operation (minimum 25/40