Maintenance - Fenix ECOSUN S09 Montageanleitung Und Bedienungsanleitung

Elektrische strahlheizplatte
Vorschau ausblenden Andere Handbücher für ECOSUN S09:

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

4. Panel connection (see fig. 2)
Electricity is distributed by CYKY cables. Cables can be connected (looped) directly in box terminal panels. The distributor
must include a circuit breaker in which the distance between disconnected contacts is at least 3.5 mm for all poles. Regula-
tion is ensured by space thermostats, e.g. EBERLE with time switching according to FENIX offer, switched by power relays or
contactors. A microprocessor control system is suitable for larger objects. In special cases, regulation must be custom tailored
according to the situation (zone heating, etc.)
st
nd
ECOSUN SB30–SB36 panels can be regulated with symmetric segment switching (1
stage – central segment, 2
stage –
rd
both extreme segments, 3
stage – all off)
Any alterations made to the factory- made connection in the terminal box will result in the destruction of the heating lamellas.
As part of the warranty conditions, customers can only make alterations to that part of the terminal box which is used for
the connection of a supply cable.
The panel should not be placed directly under a fixed connection socket.
Fig. 2

5. MAINTENANCE

There is possible only cleaning of carriage body of panel by gentle brush and detergent. Do not clean radiant surface of the
panel, cleaning can cause its damage.