CONTROLS TO BE CARRIED OUT AFTER INSTALLATION
LIFT Type............................................................................Serial number...........................................
1. CHECK THAT INSTALLATION AND TIGHTNESS OF FLOOR ANCHORS ARE CORRECT
2. CHECK THAT ELECTRICAL CONNECTION IS IN COMPLIANCE TO THE NORMS
3. CHECK THAT THE PNEUMATIC SUPPLY IS CORRECT (IF INSTALLED)
4. CHECK THAT THE LIFT OPERATION IS CORRECT ACCORDING TO USER MANUAL
5. CHECK THE CORRECT FUNCTION OF THE ELECTRICAL SAFETY DEVICES
6. CHECK THE EMERGENCY BUTTON OPERATION
7. CHECK THE CORRECT INSERTING OF THE MECHANICAL SAFETY DEVICES
8. CHECK THE CORRECT INSERTING OF THE ARMS LOCKING DEVICES
9. CHECK THE CORRECT ASSEMBLING OF THE ANTI-TOE TRAPPING DEVI
10. CHECK THE PERFECT SEALING OF THE HYDRAULIC SYSTEM
11. CHECK THE CORRECT FUNCTION OF THE HYDRAULIC SAFETY DEVICES
12. CHECK THE OIL LEVEL
13. CHECK THE EMERGENCY LOWERING OPERATION
14. CHECK THE APPLICATION OF THE WARNING LABELS, AS PER LAYOUT
15. CHECK THE CORRECT LUBRICATION OF GUIDES
16. LIFT TESTING WITH MAXIMUM LOAD
17. CHECK DOCUMENTATION (user manual & declaration of conformity)
18. TRAINING OF PERSONNEL QUALIFIED TO USE THE LIFT
NOTE
Date:
GUIDELINES FOR THE INSTALLATION ENGINEER
User:
Stamp and Signature
YES
NO
NOTE:
Montagetechniker:
Stempel und Unterschrift