5. Before starting the equipment

Before you connect the equipment to the mains
supply make sure that the data on the rating
plate are identical to the mains data.
Always pull out the power plug before making
adjustments to the equipment.
The cable hoist is not suitable for transporting
hot and/or molten masses and in addition it is not
suitable for use at low temperatures or in
aggressive atmospheres.
It is in mechanical group M1.
The service life of the cable hoist is
approximately 8000 cycles (excluding wearing
parts). When the hoist has completed 8000
cycles, all its mechanical parts must be checked
and overhauled.
Read and absorb the operating instructions
before you use the cable hoist.
Ensure that the operator knows how the machine
works and how it should be operated.
The user should always operate as set out in the
operating instructions.
The cable hoist is not designed for continuous
operation. Its mode of operation is: Intermittent
mode without influencing the starting process.
The rated capacity of the machine does not vary
due to the position of the load.
5.1 Unpacking
After opening the packaging, inspect the frame, the
steel cable, the hook and the electric control
mechanism for signs of possible transit damage.
5.2 Assembly (Fig. 5)
The cable hoist is fitted with two fastening bars (1)
with which it has to be fastened to a rectangular
tube. The dimensions of the arm must conform with
the size of the fastening bars (1) and must be
capable of supporting twice the rated load. We
recommend that you seek advice from a qualified
technician.
All screws must be tightened correctly. A qualified
technician should check the anchoring of the arm
before the machine is started.
5.3 Block and tackle function (Fig. 6 – 9)
The cable hoist is fitted with a return roller (15) and
an additional hook (16). If these parts are used
correctly, the cable hoist can lift twice its rated load.
Fit the return roller (15) and additional hook (16) as
shown in Figure 6 – 8. The permanent hook (8) must
be attached to the fastening hole (2) (Fig. 9).
The load is now raised by two steel cables, which
means that the cable hoist can lift twice its rated
load.
16.10.2008
16:07 Uhr
Seite 13

6. Operation

6.1 Information for operation
1. Remove the adhesive tape from the drum (3)
before using the hoist for the first time.
2. The value of the A-rated noise emissions at the
operatorʼs position is less than 70 dB
(determined in accordance with EN ISO 11201).
3. Supply voltage: 230 V ± 10%, 50 Hz ± 1%.
4. The cable hoist must be operated in ambient
temperatures of between 0°C and 40°C with a
relative humidity of less than 85%. Height above
sea level: max. 1,000 m.
5. The temperature for transport and storage may
be between -25°C and 55°C. The maximum
temperature must not exceed 70°C.
6. The user should lift the load off the ground at the
slowest possible speed. The cable should be taut
when the load is raised.
7. The motor (14) for the cable hoist is fitted with a
thermostat switch. Whilst the cable hoist is
operating, the motor (14) may therefore stop. It
will restart automatically when it has cooled
down.
8. The electric cable hoist is not fitted with a rated
power limiter. You should therefore not repeat
attempts to lift a load if the overload trip is
limiting the hoistʼs operation. In this case the load
exceeds the rated capacity of the cable hoist.
9. Do not leave any suspended loads unsupervised
without first taking the appropriate safety
precautions.
10. Fit the machine with a 10 A fuse or a 10 A
residual current operated circuit breaker (RCCB)
to protect the circuit
11. Do not use the lever (4/5) as a routine stopping
device. It should only be used to stop the
machine in an emergency.
12. Before you start, ensure that the steel cable (6)
is correctly wound around the drum (3) and that
the spacing between the windings is smaller than
the steel cable (Fig. 3)
13. Ensure that the load is correctly secured to the
hook (8) or, if you are using the block and tackle,
the additional hook (16) and always maintain a
safe distance from the load and the steel cable
(6).
6.2 Operation (Fig. 9)
Check whether the Emergency Stop switch (9) is
pressed. Turn the red stop switch clockwise to
release it.
Press the pushbutton ▲ (10) to raise the load.
Press the pushbutton ▼ (10) to lower the load.
Automatic stop mechanism lever (5): When the
GB