6.2
Performing the pressure test and the function test
1. Apply 6 bar of pressure to the system for a period of two hours.
2. Perform a leak test after two hours.
- The pressure drop must not exceed 0.2 bar.
3. Fill the system with water until the operating pressure is reached.
6.3
Adjusting the flow valves
6.3.1
With flow meter
Commissioning
A
1. Open the flow valve until the cal-
culated water volume (A) is indi-
cated at the flow meter.
2. Turn the ring all the way to the
mechanical stop of the flow valve.
ProCalida® IN 1½
EN
13