INSTRUCTIONS FOR INSTALLING KELLY FREESTANDING
Operation 1:
Reduce the paper template to the dimensions of the bath ordered and trim the floor
drain template. Position the paper template to decide the point of arrival of the drain
hose (fig. 1) which must be inside the floor drain, then mark the shape on the floor.
The bath must be at least 40 cm from the wall on one side and 40 cm on the other to
allow handling.
Fig.1
Floor drain
Operation 2:
Position the polystyrene floor drain template (50x30x14H cm) before preparing the bed
and screed (fig. 2). The drain must be 13 cm below floor level. If the bath is to be
installed on an existing floor, use the template to cut the floor and bed. The floor drain
will house the siphon and water drain hose.
Fig.2
Floor drain template
9
13 cm
Floor drain