Specifications of cable
Maximum permissible cable lengths to the detectors
and the room unit:
Copper cable 0.6 mm dia.: 30 m
2
Copper cable 0.5 mm
:
2
Copper cable 1.0 mm
:
2
Copper cable 1.5 mm
:
Installing and wiring the base
Wall mounting
1. Separate base from the controller
2. Hold base against the wall. Marking TOP must be
at the top!
3. Mark fixing holes
4. Drill the holes
5. If required, knock out holes on the base for fitting
cable entry glands
6. Secure base with the screws
7. Wire up the base.
Rail mounting
1. Fit the rail
2. Separate base from the controller
3. If required, knock out holes on the base for fitting
cable entry glands
4. Fit base to the rail. Marking TOP must be at the
top!
5. If required, secure the base (depending on the
type of rail used)
6. Wire up the base
Flush panel mounting
Maximum thickness of panel: 3 mm
Panel cutout required:
138 x 92 mm (+1 mm / -0 mm)
1. Separate base from the controller
2. If required, knock out holes on the base for fitting
cable entry glands
3. Insert base in the panel cutout from behind until
stop is reached. Marking TOP must be at the top!
4. Push lateral tongues behind the front panel (see
illustration below)
5. Wire up the base. Make sure the cable lengths
will be sufficient so that the control panel door
can be opened
Wrong
Place tongues correctly on the left and on the right; they
may not protrude inside the cutout!
CE2G2466X
50 m
80 m
120 m
Correct
Securing the controller to the base
1. Make sure that position and orientation of the
turning levers are correct, using the fixing screws
(illustration below shows the lateral wall of the
controller housing)
2. Insert controller in the base until stop is reached.
Marking TOP must be at the top!
3. Tighten fixing screws gradually
Commissioning
Plant-specific settings
Use setting knob
for setting the heating curve
slope. The coding switches and setting potentiome-
ters for the plant-specific settings are accessible af-
ter opening the cover.
Exercise caution with underfloor and ceiling
heating systems!
The limit thermostat must be correctly set. During the
functional check, the flow temperature may not ex-
ceed the maximum permissible level (usually 55 °C).
If it does, proceed immediately as follows:
-
Either switch off the pump, or
-
Close the pump isolating valve
Functional check
1. Check wiring to ensure it agrees with the plant
connection diagram
2. Switch on power supply
3. Check the room unit:
-
If the room unit does not respond or does not
display anything: see if wiring is interrupted
-
A short-circuit can be detected only in that the
control system stays in the standby mode.
Check wiring!
-
If there is a general fault status signal, see if
the boiler temperature is correct
4. Interrogate the boiler temperature on the room
unit:
-
Display must be correct
-
The display of --- means a short-circuit or inter-
ruption of wiring
5. Interrogate the outside temperature on the room
unit:
-
Display must be correct; if not, check wiring for
interruptions
-
The display of --- means a short-circuit or inter-
ruption of wiring
7