9 Test Run

The following illustrates the test run of the PV inverter.

9.1 Check Before Turning On

●The AC cable has been correctly connected.
●All of the DC cables extending from the strings have been connected.
Also, any and all unused cable glands are closed with protective caps on
the bottom of the PV inverter.
●The front panel is securely attached to the PV inverter.

9.2 Test Run Procedure

The following procedure should
be performed after making sure
that your PV modules are receiv-
ing light and no blackout is
encountered.
1 Turn on the DC disconnector.
LCD
Liquid crystal display(LCD)
POWER
MODE
switch
switch
Check/Action
Wait for 20 seconds. Then the display
shown to the left should appear on the LCD.
(If no information is displayed, see p.51
"Troubleshooting".)
49
ERROR
LED
SELECT
ENTER
switch
switch
pp.1-48
pp.1-48
pp.1-48